PennDOT – District 1 News

Oliver Road Roundabout Project in Summit Township, Erie County Continues with Detour Starting Next Month

​The $3.8 million project to build a roundabout at the intersections of Oliver Road (Route 4008), Flower Road, and Hamot Road (Route 4010) in Summit Township, Erie County continues with the first detour slated to start in August.

 

The two-year project will include removal of the existing intersections and construction of roundabout. Additional work includes milling and paving intersecting roads, construction of sidewalks, ADA curb ramps, drainage improvements, environmental mitigation, lighting, vegetation replacement, and pavement markings.

 

Work will be done in seven phases and various detours will be in place during those phases.

 

Phase 1 started June 21 and includes the construction of the offline portion of the roundabout. Work also includes new roadway approaches, drainage, sidewalks, and concrete islands. The truck detour originally planned for this phase will no longer be implemented. Work is expected to take approximately 40 days to complete.

 

Following the work, construction will focus on the Hamot Road north approach to the new roadway and the removal of the unused portion of Hamot Road. Temporary lanes will be constructed for two-lane traffic on Hamot Road. Additional drainage work will also be done. Traffic on Hamot Road will be detoured using Route 19 (Peach Street) and Hershey Road.  The detour is expected to be in place starting August 24, 2021. Work is expected to take approximately eight days.

 

Phase 2 will include the construction of the approach on Oliver Road, as well as drainage, sidewalks, and concrete islands. Traffic will use the temporary lanes on Hamot Road. Work is expected to take approximately 12 days to complete.

 

Once it is complete work will start on the tie-in between Oliver Road approach and the new roadway. Work will also include the removal of a portion of the existing Oliver Road as well as drainage and sidewalks. Oliver Road traffic will be detoured using Hamot Road, Hershey Road, and Route 19. Work is expected to take approximately 11 days.

 

Phase 3 will include the construction of the tie-in between Flower Road approach and new roadway. Work will also include the removal of a portion of the existing Flower Road as well as drainage and sidewalks. Flower Road traffic will be detoured using the Oliver Road, Dunn Valley Road (Route 4013), and Reichert Road (Route 4013). Work is expected to take approximately 15 days.

 

Work is expected to shutdown for the winter following Phase 3. Temporary pavement markings and traffic control devices will be in place and all detours will be lifted during the winter months.

 

Phase 4 is expected start in mid to late April 2022, weather permitting. Work will include removing another portion of the existing Oliver Road approach and construction of the tie-in between Oliver Road and the new roadway. Traffic on Oliver Road and Hamot Road will be detoured using Flower Road, Reichert Road, and Dunn Valley Road. Work is expected to take approximately 14 days.

 

Phase 5 will include constructing the southern tie-in between Hamot Road and the new roadway. Drivers should be alert for changing traffic patterns and detour signs. Work will require varying detours between Oliver Road and Hamot Road. Work is expected take approximately 10 days.

 

Phase 6 will include constructing the central island including the truck apron, curbs, and landscaping. Work is expected to take approximately 28 days to complete.

 

Phase 7 will include milling and paving the final surface for the roundabout lanes, as well as sign installation.

 

The roundabout is expected to be fully open to all traffic in July 2022.

 

Throughout the project, motorists may encounter lane restrictions with traffic controlled by flaggers. Drivers should be alert for traffic pattern shifts, lane restrictions, and detour signs.

 

PennDOT urges motorists to slow down when driving in work zones, and also to be alert to changing conditions, avoid distractions and to pay attention to signs and flaggers. Drive responsibly in work zones for your safety and the safety of the workers.

 

The contractor is J.C. Lee Construction and Supply of Petrolia, PA. The contract cost is $3,883,146, which is to be paid entirely with federal funds.

 

Information on the project, including detour updates and progress pictures, is available online at www.penndot.gov/district1 by clicking on the Construction Projects/Roadway link under the Resources heading, picking the Erie County box then choosing the Oliver Road Roundabout Project tile.

 

Motorists can check conditions on major roadways by visiting www.511PA.com. 511PA, which is free and available 24 hours a day, provides traffic delay warnings, weather forecasts, traffic speed information and access to more than 1,000 traffic cameras.

 

511PA is also available through a smartphone application for iPhone and Android devices, by calling 5-1-1, or by following regional Twitter alerts accessible on the 511PA website.

 

Subscribe to PennDOT news and traffic alerts in Crawford, Erie, Forest, Mercer, Venango, and Warren counties at www.penndot.gov/District1.

 

Information about infrastructure in District 1, including completed work and significant projects, is available at www.penndot.gov/D1Results. Find PennDOT’s planned and active construction projects at www.projects.penndot.gov.

 

Follow PennDOT’s northwest region on Twitter at www.twitter.com/511PAErie or Facebook at https://www.facebook.com/groups/northwestregionpenndot.